Guide · Maharashtra
MSEDCL net metering: how to apply
What it takes to get rooftop solar net-metered with MSEDCL (Maharashtra State Electricity Distribution Co. Ltd.) in Maharashtra — the application process, the bidirectional meter, the typical timeline, and where to apply.
- •MSEDCL is one of India's largest rooftop-solar DISCOMs by installed homes.
- •Smaller systems are fast-tracked; larger systems go through a feasibility check on your sanctioned load.
The MSEDCL net-metering process, step by step
- 1
Apply on the national rooftop-solar portal
Register with your electricity account number and choose MSEDCL as your DISCOM. This starts your subsidy application.
- 2
MSEDCL feasibility check
MSEDCL verifies your connection and sanctioned load. Systems up to 3 kW skip this separate approval step.
- 3
Install through a registered vendor
A registered installer sets up your system and files the net-metering request with MSEDCL on your behalf.
- 4
Inspection & bidirectional meter
MSEDCL inspects the installation and fits a bidirectional (net) meter that records both the power you import and the power you export.
- 5
Commissioning & net metering activated
Once commissioned, your exported units begin offsetting the units you draw from the grid.
- 6
Subsidy credited to your bank
The central rooftop-solar subsidy is transferred directly to your bank account after commissioning — it is not deducted upfront.
Typical timeline
Most homeowners see MSEDCL approvals in a few weeks, with the subsidy credited about a month after commissioning. Timelines vary by circle and sanctioned load.
Rules and timelines change. Last verified 2026-07-08. MSEDCL website · National rooftop-solar portal
See what solar saves — and let an installer handle MSEDCL
Run a free estimate for your home, then compare Maharashtra installers who manage the MSEDCL net-metering application for you.
MSEDCL net metering — frequently asked
Who applies for MSEDCL net metering — me or my installer?
Your registered installer usually files the MSEDCL net-metering application and arranges the bidirectional meter as part of the project. Confirm it is included when you compare quotes.
How long does MSEDCL net metering take?
Typically a few weeks for approvals, plus about a month for the subsidy to be credited after commissioning. It varies by circle and sanctioned load — treat MSEDCL's portal as the source of truth for current timelines.
Do I need feasibility approval for a small rooftop system?
For systems up to 3 kW the separate technical-feasibility approval is generally waived, which speeds up the whole process.
Which meter do I need for net metering?
A bidirectional (net) meter that records both the power you import from and export to the grid. MSEDCL installs it during the inspection step.
Does the subsidy come through MSEDCL?
The central rooftop-solar subsidy is transferred directly to your bank account after commissioning. MSEDCL handles the grid connection and the net meter, not the subsidy payout.